The Regional Power Transmission Interconnection Project (RPTIP) was one of the key projects which DV has done the technical audit of the mentioned project. The project was audited both financially and in technical to assure compliance with MEW and Donor requirements.
- Duration of Assignment
03 Months
- Client
Ministry of Energy and Water (MEW) and Asian Development Bank (ADB)
- Start Date / Completion Date
Mar/2015 – May/2015